CONSTRUCTION PERMIT BY RAJUK

A Construction Permit issued by RAJUK (Rajdhani Unnayan Kartripakkha) is an official approval allowing individuals or entities to commence construction activities within designated areas. Governed by the Town Improvement Act 1953, this process involves plan reviews, compliance checks, and adherence to building codes. The permit ensures that structures are safe, meet regulatory standards, and contribute to urban development while promoting orderly growth and maintaining the aesthetic and structural integrity of the city. The Act provides the legal framework for RAJUK to regulate urban development, review construction plans, enforce building codes, and grant permits based on compliance with established guidelines.

Issuing Authority

Name : Rajdhani Unnayan Kartripakkha (RAJUK)

Address : 01, Rajuk Avenue, Motijhil, Dhaka-1000

Email: chairman@rajukdhaka.gov.bd

Website : www.rajukdhaka.gov.bd

Required list of all documents

  1. Main deed of land [Showing the original copy, a photocopy of the original has to be submitted]
  2. Bia deed of land [Showing the original copy, a photocopy of the original has to be submitted]
  3. Bangladesh survey (BS) Lessor [Available at RAJUK (to be collected be applicant)]
  4. The above three documents are required for the No Objection Certificate (NOC) [From RAJUK]
  5. Plan and NOC for plan approval [Original]

Step by step all process

Step 1: Submission of Supporting Documents: The applicant initiates the process by submitting necessary supporting documents to RAJUK. These documents typically include architectural drawings, structural plans, land ownership documents, and any other required paperwork stipulated by RAJUK.

Step 2: Issuance of NOC (No Objection Certificate) by RAJUK: Upon review of the submitted documents, RAJUK assesses the proposed construction plans against regulatory requirements, urban development policies, and safety standards. If the plans meet all criteria, RAJUK issues a No Objection Certificate (NOC). The NOC signifies RAJUK’s approval for the proposed construction within designated areas.

Step 3: Plan Approval by RAJUK: Following the issuance of the NOC, RAJUK proceeds to review the detailed construction plans in-depth. This review ensures that the proposed construction complies with building codes, zoning regulations, environmental guidelines, and other relevant laws. Upon satisfactory review, RAJUK grants formal approval for the construction plans.

Step 4: Commencement of Construction According to Approved Plans: With the approved construction plans in hand, the applicant can commence construction activities within the specified parameters set by RAJUK.

Free schedule

Application Form fee BDT 300.00

Land clearance Form fee BDT 1000.00

Official time limit

6 months to 1 year

Actual time limit